Project Details & Costing

PROJECT DETAILSPROJECT EXECUTION
131 Bedded Specialized Center of Excellence6 month Architecture Drawing
2 OT, 2 CATH, 1 Hybrid OT/LAB3 months LDA approvals
30 Bed Surgical ICU/20 Bed M ICU18 Months Civil works​
School of nursing3 Month equipment ordering
Doctors accommodation3 years completion time
100 % Technology driven​2.3 B PKR
No Charge to local patient
10% Bed for International Medical Tourism
Targeted 800 to 1000 Surgeries per annum

Covered Area Cost

FacilityRooms/Beds/FacilitiesArea in Sqft
Emergency Ward104,656
Pre Opp Ward52,328
Angio/Post Opp Holding Ward103,725
Operation Theater310,500
CATH LAB26,000
Hybrid LAB13,000
Cardiac Surgical ICU Rooms3012,576
Cardiology ICU Ward/Rooms207,450
Floor Beds/Rooms5022,020
OPD rooms Medical & Surgical63,252
ECHO Room1442
MRI Room1900
Angiography Room11,050
Doctors room104,420
Nurses rooms/stations56,000
On Site Lab13,000
Hospital Facilities51,100
TOTAL142,418

Overall Cost

 Estimates in PKR Conversion RateEstimates in US$
Total No. Of Beds131
Total Covered Area (In Sqft)142,418
Total No. of Floors
8 (2 Basement, 1 Ground & 5 upper floor)
Design & Architecture20,143,068140143,879.06
Total Construction Cost1,216,295,9601408,687,828
Total Cost of Equipment1,079,900,0001407,713,571
Total Cost Without Land2,316,339,02814016,545,279
Note: Cost of construction is based on data from
1) Indus Hospitals
2) Akhuwat Foundation
3) AAA Management Consultant

Hospital Construction Cost

  Estimates in PKREstimates in US$
Total Covered AreaSqft142,418
No. of Floors
(Basement 1, 2, G/Floor, 1st Floor & 4 Floor)
8
Design & ArchitectureRs20,143,068143,879
Cost of Grey StructureRs574,596,5604,104,261
Cost of FinishingRs641,699,4004,583,567
Total Cost of ConstructionRs1,236,439,0288,831,707
Per Sqft design & architectureRs1411.01
Per Sqft Grey structure costRs4,03528.82
Per Sqft Finishing costRs4,50632.18
Total per Sqft construction costRs 8,68262.01
Note: Cost of construction is based on data from
1) Indus Hospitals
2) Akhuwat Foundation
3) AAA Management Consultant

Hospital Equipment Cost

 Estimates PKREstimates in US$
Operation theater (3OT)90,000,000642,857
CATH LAB400,000,0002,857,143
Post Opp/Angiography Ward15,000,000107,143
Hybrid LAB50,000,000357,143
Emergency Ward35,000,000250,000
Per Opp wards2,500,00017,857
ICU Surgical105,000,000750,000
ICU Cardiology40,000,000285,714
Floor Beds/Rooms10,000,00071,429
Diagnostic Center247,200,0001,765,714
Facilities64,750,000462,500
CCTV & Invigilation 15,000,000107,142.86
Furniture & Fixtures Total4,700,00033,571
Total1,079,150,0007,708,214